2024 PLANNED ROAD PROJECTS

Road Work Ahead sign

SEAL COATING

The following roads are scheduled for Chip Sealing this year:

  • Champion Run
  • Northern Dancer Run
  • Kentucky Oak Way
  • Mary Hill Dr.
  • Bette Ann Dr.
  • Linda Ann Dr.
  • Red Fox Run
  • Deer Trail
  • Beaver View
  • Cindy Ln.
  • Cindy Ct.
  • Irene Ln.
  • County Ln.
  • Lillian Dr.
  • Miranda Way
  • Rybeck Rd.

Once the dates have been determined, the website will be updated and something will be out to the email list.

Contact the Town of Merton DPW Department at 262-966-2118 with any questions or concerns.

TAMRON RIDGE SUBDIVISION RECONSTRUCTION starting May 6, 2024.

A letter was sent out informing property owners that in 2024 there will be a major road project in Tamron Ridge Subdivision.

Payne & Dolan will be the contractor and the work will begin most likely in late spring or early summer. 

Planned start date is May 6, 2024.

Roads will be open during reconstruction and the project should take about 6 to 8 weeks, if weather cooperates.

If you have any questions, please call the DPW at 262-966-2118

 

CRACK FILLING FOR 2024 Starting May 8th, 2024

Crack filling will start May 8 for the roads listed below.

Please watch out for construction worker during this time period.

Work should be completed in three to four days weather permitting.

Camp Whitcomb Rd

Dorn Rd.

Rybeck Rd.

Irene Ln.

Maes Walke Subdivision

Click any thumbnail image to view a slideshow

crack filling